[News] Datasection Slashes Forecast Nearly 90%, Raising Questions Over Taiwanese Suppliers’ B200/B300 Orders
Concerns are spreading across the AI infrastructure supply chain. Beyond Southeast Asia, where tighter U.S. export controls are weighing on data center operators, Japan’s Datasection has slashed its full-year revenue forecast by nearly 90%, raising questions about delivery disruptions for the Taiwanese server makers that supplied its data centers, Commercial Times reports.
What Happened
Datasection cut its forecast for the fiscal year ending March 2027 by 89.3%, from JPY 162.2 billion to JPY 17.3 billion, and now expects a net loss of JPY 1.48 billion. In its filing, it cited the cancellation of a JPY 79.9 billion order and delays at one domestic and two overseas AI data centers that were due to begin phased operations in July 2026.
Separately, the owner of an overseas facility, whose launch had been delayed by prolonged talks with its customer over revised terms including a switch from NVIDIA B200 to B300 servers, gave notice on August 31 that it would terminate the lease.
Taiwanese Suppliers’ exposure
Citing Datasection’s earlier procurement disclosures, Commercial Times highlights several large orders awarded to Taiwanese manufacturers, whose delivery schedules could face adjustments.
On B200 servers, GIGABYTE subsidiary Giga Computing secured an order for 625 units, while ASRock Rack was tapped to supply 587 for a project in Thailand, the report notes. On B300 servers, Inventec landed a 1,250-unit order for a Sydney data center, while Compal was selected to deliver 635 units to a facility in Inzai, Chiba Prefecture, with installations beginning in July.
Tencent Link under Scrutiny
The downgrade has also drawn attention to Datasection’s reported ties with Chinese tech giant Tencent. Asked about the relationship, CEO Norihiko Ishihara stopped short of confirming or denying it, telling Barron’s, as cited by Economic Daily News, “I’m not saying yes, and I’m not saying no.” The filing does not name the customer behind the cancelled order.
The connection had surfaced earlier. According to a December 2025 Chosun Biz report citing the Financial Times, Datasection’s data center near Osaka, equipped with 15,000 NVIDIA Blackwell B200 GPUs, was effectively dedicated to Tencent, which reportedly secured three years of access through a third-party intermediary under a $1.2 billion deal. Datasection also planned facilities in Sydney, Australia, with Tencent expected to be the main customer, the report added.
Export Controls Add a Separate Risk
Tighter U.S. rules could further complicate Datasection’s overseas expansion, Commercial Times notes. Under another set of rules from the U.S. Commerce Department’s Bureau of Industry and Security (BIS), overseas data centers must obtain U.S. approval before providing computing capacity above 12 million Total Processing Performance (TPP) to customers in mainland China, Macau and other restricted countries, according to another Commercial Times report. The threshold is roughly equivalent to 760 NVIDIA H100 or 330 B200 chips, the report suggests.
The supply chain is already feeling the effect. Nikkei reports that NVIDIA’s Grace Blackwell GB200 NVL72 server racks start at nearly $5 million, while individual B200 GPUs are priced from $500,000. Both remain popular among Southeast Asian customers. Notably, at least two NVIDIA server partners have reportedly halted shipments to the region following the latest U.S. export restrictions, Nikkei suggests.
Read more
- [News] U.S. Targets China’s AI Compute Loophole, Tightens Chip Exports to Malaysia, Singapore and Three Others
- [Deep Dive] Beyond Megaspeed: Southeast Asia’s China-Linked AI Compute Network in Spotlight—Key Players at a Glance
(Photo credit: Datasection’s LinkedIn)