[News] SK hynix’s Indiana Plant Clears Nearly Two-Year Rezoning Dispute Ahead of 2029 Production


2026-11-24 Semiconductors editor

As SK hynix presses ahead with its U.S. expansion, a key legal hurdle has been cleared. According to Korea Credit News, the West Lafayette City Council in Indiana has approved a settlement with local residents, ending a nearly two-year dispute over the industrial rezoning of the company’s advanced semiconductor packaging plant site.

The report explains that the dispute began after SK hynix announced plans to invest $3.87 billion (approximately KRW 5.4 trillion) in a semiconductor packaging plant on a 90-acre site near Purdue University. While originally zoned for residential use, the city council, in May 2025, voted 6–3 to rezone the property for heavy industrial use, prompting three nearby residents to file a lawsuit against the city.

As highlighted by Korea Credit News and The Tracker, the city council subsequently voted to bring the lawsuit to a close on November 19, effectively canceling the trial originally scheduled for December 1.

The decision, per The Tracker, could help SK hynix preserve a critical window for investment and capacity expansion, as semiconductor manufacturing requires years of lead time, from initial investment decisions and plant construction to equipment installation and the eventual start of mass production.

Notably, the agreement includes a clause barring both sides from making disparaging remarks related to the lawsuit for the next two years, according to Korea Credit News.

SK hynix’s Current Progress in Indiana

The memory giant has already reached a key milestone for U.S. manufacturing earlier in August. According to SK hynix’s press release, the company marked the start of construction on its Indiana fab with an August 27 groundbreaking ceremony at Purdue University’s Holloway Gymnasium in West Lafayette.

As reported by Reuters, SK hynix plans to begin mass production of next-generation HBM4E chips at its Indiana facility in the third quarter of 2029, with CEO Kwak Noh-Jung expecting the plant to eventually achieve an annual production capacity of hundreds of thousands of wafers.

SK hynix expects its Indiana facility, located at Purdue Research P, Reuters reports, adding that cleanroom operations are slated to begin in the second half of 2028.